VCMRR #32 · Revision Request
VCMRR032 Calculation of Average Running Hours per Start when Determining the Variable O&M for QSGRs
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2021-11-03
Approved2022-02-10
Sections Affected
Appendix 7
Summary
This Verifiable Cost Manual Revision Request (VCMRR) clarifies that the average run time per start is calculated by dividing the total running hours by the total number of starts during the 20 consecutive day period, and ensures that at a minimum, one start will be used in the calculation of the average run time per start when the Resource is operating on the first interval of the first day of the 20 consecutive day period.
Timeline
- Oct 19 '21
-
Nov 3 '21
WMS WMS Meeting by Webex OnlyWMSRecommended for Approval Recommended for approval“to recommend approval of VCMRR032 as submitted” — Passed→ Impact Analysis Consideration
-
Dec 1 '21
WMS WMS Meeting by Webex OnlyWMSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 11/3/21 WMS Report and Impact Analysis for VCMRR032” — Passed→ Revision Request Consideration
-
Jan 31 '22
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 11/3/21 WMS Report and Impact Analysis for VCMRR032” — Passed→ Revision Request Consideration
-
Feb 10 '22
PUCTPUCTApproved Approved“to approve VCMRR032 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization.” — Passed
-
—