VCMRR #8 · Revision Request
VCMRR008 Alignment with NPRR700, Utilizing Actual Fuel Cost in Startup Offer Caps
ReasonAddresses current operational issues, Market efficiencies or enhancements
Created2015-06-03
Sections Affected
3Appendix 5
Summary
NPRR700 revises Protocols to incorporate actual fuel costs into the Day-Ahead Market (DAM) and Reliability Unit Commitment (RUC) procurement process and DAM Make-Whole Payment calculations. This Verifiable Cost Manual Revision Request (VCMRR) aligns the Verifiable Cost Manual with the provisions proposed by NPRR700.
Timeline
-
Apr 29 '15
WMSFiled by RCWG
-
May 6 '15
Listed without action at 1 meeting
- Jun 3 '15
-
Jul 8 '15
WMS WMS MeetingWMSRecommended for Approval Recommended for approval Amended by the Jun 26 '15 ERCOT comments“To recommend approval of VCMRR008 as amended by the 6/26/15 ERCOT comments.” — Passed→ Revision Request Consideration
-
Jul 30 '15
TAC TAC MeetingTACDeferred/Tabled Tabled“To table VCMRR008.” — Passed→ Revision Request Consideration
-
Aug 27 '15
TAC TAC MeetingTACApproved Recommended for approval“To approve VCMRR008 as recommended by WMS in the 7/8/15 WMS Report.” — Passed