SMOGRR #23 · Revision Request
SMOGRR023 Updates to Nameplate Information Requirements
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2020-09-02
Sections Affected
3.2.37.5.2and 7.5.6 (delete)
Summary
This Settlement Metering Operating Guide Revision Request (SMOGRR) provides an option for certification of nameplates of newly installed or replaced instrument transformers by a professional engineer when nameplate photos cannot be physically accessed because the instrument transformers are installed inside other equipment apparatus, replaces a list of instrument transformer nameplate data requirements with a reference to the Institute of Electrical and Electronics Engineers (IEEE) standards, and deletes Section 7.5.6.
Timeline
- Aug 18 '20
-
Sep 2 '20
WMS WMS MeetingWMSRecommended for Approval Recommended for approval“to recommend approval of SMOGRR023 as submitted” — Passed→ Impact Analysis Consideration
-
Oct 7 '20
WMS WMS Meeting by Webex OnlyWMSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 9/2/20 WMS Report and Impact Analysis for SMOGRR023” — Passed→ Revision Request Consideration
-
Oct 28 '20
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to approve SMOGRR023 as recommended by WMS in the 10/7/20 WMS Report” — Passed→ Revision Request Consideration
-
—
Posted since the last meeting