ERCOT·WATCH Search ercot.com  ⌕
SMOGRR #10 · Revision Request

SMOGRR010  Synchronization with NPRR291, Reduce the Comment Period for NPRRs and SCRs

Approved sponsor ERCOT posted 2011-01-07 ercot.com
ReasonAs a result of the Technical Advisory Committee (TAC) structural and process review, TAC requested ERCOT staff to draft an NPRR to reduce the comment period for NPRRs to 14 days. Since SMOGRRs have a similar initial comment period, proposed revisions to the SMOG revision process are included in this SMOGRR to align with the Nodal Protocol revision process.
Created2011-02-11
Sections Affected
10.4.3
Summary
This Settlement Metering Operating Guide Revision Request (SMOGRR) reduces the comment period for SMOGRRs from 21 days to 14 days and removes the requirement for the comment period to end at least three Business Days prior to the next regularly scheduled Metering Working Group (MWG) meeting.
Timeline