SMOGRR009  Submittal Timeline for EPS Metering Design Proposals

Approved sponsor ERCOT posted 2010-07-15 ercot.com
ReasonThe submittal timeline in the SMOG in regards to EPS Metering Design Proposals will need to change to reduce risk associated with ERCOT generating production-ready network models.
Created2010-08-17
Sections Affected
3.2.1
Summary
This Settlement Metering Operating Guide Revision Request (SMOGRR) changes the timeline for Transmission and/or Distribution Service Provider (TDSP) submittal of ERCOT-Polled Settlement (EPS) Metering Design Proposal.
Timeline