ERCOT·WATCH Search ercot.com  ⌕
SCR #821 · Revision Request

SCR821  Voltage Set Point Target Information for Distribution Generation Resource (DGR) or Distribution Energy Storage Resource (DESR)

Approved sponsor AEP SC posted 2022-03-29 ercot.com
ReasonAddresses current operational issues
Created2022-04-14
Approved2023-01-26
Summary
This System Change Request (SCR) allows, at the option of the Transmission and/or Distribution Service Provider (TDSP), Voltage Set Point target information to be provided to a Distribution Generation Resource (DGR) or a Distribution Energy Storage Resource (DESR) installation.
Timeline