SCR #805 · Revision Request
SCR805 Provide Early Access to Certain 60-Day Reports to TSPs Upon Request
ReasonAddresses current operational issues; Meets Strategic goals
Created2019-09-12
Approved2019-12-10
Sections Affected
Nodal Protocol Section 1.3.6Exceptions
Summary
This System Change Request (SCR) will allow ERCOT to automatically provide certain reports to requesting Transmission Service Providers (TSPs) prior to the date the reports are posted to the Market Information System (MIS) Public Area (i.e., 60 days after the Operating Day). The reports will be provided only to TSPs that make a formal request to ERCOT. Once the formal request is approved by ERCOT, ERCOT will automatically provide these reports on an ongoing basis to the TSP. The content provided will be similar to the content provided in the following reports: • NP6-619-ER State Estimator 60-Day Delayed Transmission Line Flows • NP6-622-ER State Estimator 60-Day Delayed Transformer Information • NP3-965-ER 60 Day SCED Disclosure Reports (Only actual generation portion of this report)
Timeline
- Aug 28 '19
-
Sep 12 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“to recommend approval of SCR805 as submitted” — Passed→ Impact Analysis Consideration
-
Oct 10 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2020 · rank 2920“to endorse and forward to TAC the 9/12/19 PRS Report and Impact Analysis for SCR805 with a recommended priority of 2020 and a rank of 2920” — Passed→ Revision Request Consideration
-
Oct 23 '19
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of SCR805 as recommended by PRS in the 10/10/19 PRS Report” — Passed→ Revision Request Consideration
-
Dec 10 '19
BOARD Board of Directors MeetingBOARDApproved Approved“to approve SCR805 as recommended by TAC in the 10/23/19 TAC Report” — Passed
-
—
Posted since the last meeting