SCR #800 · Revision Request

SCR800  Addition of DC Tie Ramp to GTBD Calculation

Approved sponsor ERCOT posted 2019-04-24 ercot.com
ReasonMarket efficiencies or enhancements
Created2019-05-09
Approved2019-12-10
Summary
This System Change Request (SCR) incorporates Direct Current Tie (DC Tie) scheduled ramp into Security-Constrained Economic Dispatch (SCED) by updating the formula used by the Resource Limit Calculator (RLC) to calculate the Generation To Be Dispatched (GTBD) value to include the addition of a scheduled 5-minute DC Tie ramp rate (DCTRR). This DCTRR will be calculated from the scheduled system-wide DC Tie ramp times five and a configurable factor to capture the scheduled 5-minute DC Tie ramp.
Timeline