SCR #799 · Revision Request
SCR799 ERCOT Outage Study Cases in the System Operations Test Environment (SOTE)
ReasonMarket efficiencies or enhancements
Created2019-03-14
Approved2019-06-11
Sections Affected
None
Summary
This System Change Request (SCR) enables ERCOT to provide its current month, 60 day, and 90 day Outage study cases in the System Operations Test Environment (SOTE) on a monthly basis for Transmission Service Providers (TSPs).
Timeline
- Feb 26 '19
-
Mar 14 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“to recommend approval of SCR799 as submitted” — Passed→ Impact Analysis Consideration
-
Apr 11 '19
PRS PRS MeetingPRSDeferred/Tabled Tabled“to table SCR799” — Passed→ Impact Analysis Consideration
-
May 9 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2019 · rank 2710“to endorse and forward to TAC the 4/11/19 PRS Report and the Impact Analysis for SCR799, with a recommended priority of 2019 and rank of 2710” — Passed→ Revision Request Consideration
-
May 22 '19
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of SCR799 as recommended by PRS in the 5/9/19 PRS Report and the Revised Impact Analysis” — Passed→ Revision Request Consideration
-
Jun 11 '19
BOARD Board of Directors MeetingBOARDApproved Approved“to approve SCR799 as recommended by TAC in the 5/22/19 TAC Report” — Passed
- May 29 '24
-
Aug 29 '24
Listed without action at 2 meetings (Aug 29 '24 – Sep 26 '24)