SCR #795 · Revision Request
SCR795 Addition of Intra-Hour Wind Forecast to GTBD Calculation
ReasonMarket efficiencies or enhancements
Created2017-12-14
Approved2018-04-10
Sections Affected
6.5.7.3
Summary
ERCOT is in the process of adding an intra-hour wind forecast. This System Change Request (SCR) updates the formula used by the Resource Limit Calculator to calculate the Generation To Be Dispatched (GTBD) value to include the addition of a predicted 5-minute wind ramp (PWRR). This PWRR will be calculated from the intra-hour wind forecast times five and a configurable factor to capture the forecasted 5-minute wind ramp. This addition would help Security-Constrained Economic Dispatch (SCED) take into account the potential 5-minute wind ramp in its 5-minute Base-Points and would take the burden off of Regulation to cover the 5-minute gain or loss of generation from variations in wind and instead dispatch this energy economically. This change will also aid reducing frequency recovery duration following events that occur during times with significant wind up and down ramps. Although there will be inherent forecast error in the intra-hour forecast, this change will give a better indication to SCED via GTBD of the level of wind generation that will be available in the next 5 minutes, as compared to the current assumption that the wind generation will persist at the same level as at the beginning of the 5-minute interval. Once ERCOT begins to receive the intra-hour wind forecast from its vendor(s), ERCOT will analyze the 5-minute out forecast performance and accuracy of projected wind generation ramp direction before the intra hour wind forecast component is activated in the GTBD formula.
Timeline
- Nov 28 '17
-
Dec 14 '17
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → ROS Referred → WMS“to table SCR795 and refer the issue to ROS and WMS” — Passed→ Language Consideration
- Jan 10 '18
- Jan 11 '18
- Jan 18 '18
-
Jan 31 '18
Listed without action at 2 meetings (Jan 31 '18 – Feb 1 '18)
-
Feb 8 '18
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“to recommend approval of SCR795 as submitted” — Passed→ Impact Analysis Consideration
- Feb 13 '18
-
Feb 28 '18
Listed without action at 1 meeting
-
Mar 8 '18
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2018 · rank 2200“to endorse and forward to TAC the 2/8/18 PRS Report and the Impact Analysis for SCR795 with a recommended priority of 2018 and rank of 2200” — Passed→ Revision Request Consideration
- Mar 19 '18
-
Mar 22 '18
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of SCR795 as recommended by PRS in the 3/8/18 PRS Report” — Passed→ Revision Request Consideration
-
Apr 10 '18
BOARD Board of Directors MeetingBOARDApproved Approved“approved SCR795 as recommended by TAC in the 3/22/18 TAC Report” — Passed
- Oct 22 '18