SCR #766 · Revision Request
SCR766 Load Zone and Hub LMPs Distributed by ICCP (formerly "Load Zone Price Distributed by ICCP")
ReasonTo fix the system to address some price latency issues for Loads that have been present since Nodal Go-Live.
Created2011-05-11
Sections Affected
NA
Summary
This System Change Request (SCR) allows the price data to be transferred to the Energy Management System (EMS) for distribution over Inter-Control Center Communications Protocol (ICCP) links, as soon as the five-minute Load Zone and Hub prices are calculated in Real-Time.
Timeline
-
Apr 18 '11
PRSFiled by Alice Jackson for the Demand Side Working Group (DSWG) on behalf of WMS
-
May 11 '11
WMS WMS MeetingWMSRecommended for Approval Recommended for approval Amended by the WMS comments“To recommend approval of SCR766 as revised by WMS” — Passed→ WMS recommend priority and rank and review the CBA and IA
-
Jun 15 '11
WMS WMS MeetingWMSRecommended for Approval Recommended for approval Forwarded → PRS“Endorse and forward the 5/11/11 WMS Report and Impact Analysis for SCR766 to PRS.” — Passed→ PRS consideration
-
Jun 23 '11
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC rank 40“To endorse and forward the 6/15/11 WMS Report, Impact Analysis, and Cost Benefit Analysis for SCR766 to TAC with a recommended priority of High and a rank of 40.” — Passed→ TAC consideration
-
Jul 7 '11
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of SCR766 as recommended by PRS in the 6/23/11 PRS Report.” — Passed→ ERCOT Board consideration
- Jul 21 '11
-
Aug 4 '11
Listed without action at 1 meeting
-
Aug 16 '11
BOARD Board of Directors MeetingBODNOMApproved Recommended for approval“To approve SCR766 as recommended by TAC in the 7/7/11 TAC Report.” — Passed
-
Sep 20 '11
Listed without action at 1 meeting