SCR #766 · Revision Request

SCR766  Load Zone and Hub LMPs Distributed by ICCP (formerly "Load Zone Price Distributed by ICCP")

Approved sponsor Alice Jackson for the Demand Side Working Group (DSWG) on behalf of WMS posted 2011-04-18 ercot.com
ReasonTo fix the system to address some price latency issues for Loads that have been present since Nodal Go-Live.
Created2011-05-11
Sections Affected
NA
Summary
This System Change Request (SCR) allows the price data to be transferred to the Energy Management System (EMS) for distribution over Inter-Control Center Communications Protocol (ICCP) links, as soon as the five-minute Load Zone and Hub prices are calculated in Real-Time.
Timeline