SCR #745 · Revision Request
SCR745 Retail Market Outage Evaluation and Resolution
ReasonTo achieve improved Market performance and reliability through a reduction of ERCOT Retail Systems unplanned outages
Created2005-06-15
Approved2009-02-17
Summary
In an effort to promote system reliability for the Retail Market by significantly reducing ERCOT System Outages, a technical resolution is needed. To ensure the technical recommendations in this SCR sufficiently accomplish the intention, ERCOT IT should produced a full evaluation of ERCOT systems, and a full evaluation of internal processes associated with those systems such that Retail Market Participants will be able to select the best cost-based solution able to reduce and/or eliminate ERCOT system outages.
Timeline
- May 12 '05
-
Jun 15 '05
RMS RMS MeetingRMSRecommended for Approval Recommended for approval“On 6/15/05, RMS unanimously voted to recommend approval of SCR745 with the scope to perform a full evaluation of the retail systems and determine possibilities for resolving and eliminating ERCOT retail system outages. All market segments were present.” — Passed
-
Jul 13 '05
RMS RMS MeetingRMSRecommended for Approval Action“On 7/13/05, RMS voted to expand the scope of the SCR to include recommended solutions. There was one abstention from the Independent REP segment. All market segments were present for the vote.” — Passed
-
Aug 10 '05
RMS RMS MeetingRMSRecommended for Approval Recommended for approval priority 1 · rank 1 Recommended for approval“On 08/10/05, RMS voted to recommend approval of SCR 745 and restated that SCR745 should remain a priority of 1.1. The motion passed with one nay vote from the Consumer Group. All Market segments were present. RMS also voted to recommend approval of the impact analysis with one abstention from the Consumer group. All market segments were present.” — Passed
-
Aug 24 '05
PRS PRS MeetingPWGRecommended for Approval priority 1 · rank 30“On 08/24/05, PRS concurred with RMS’s recommendation of a priority of 1.1 and a rank of 30.” — Passed
-
Sep 8 '05
TAC TAC MeetingTACRecommended for Approval Recommended for approval“On 09/08/05, TAC voted to recommend approval of SCR745 as recommended by RMS with one opposing vote from the IOU segment; and 8 abstentions from the Municipal (2), Consumers (4), and IPM (2) segments. All market segments were present.” — Passed
-
Oct 6 '05
TACEmail Vote / Unlisted MeetingTACApproved Urgent status“On 10/06/05, TAC voted to grant urgent status to SCR745 with one abstention from the Independent Power Marketer (IPM) segment. All market segments were present.” — Passed
-
Oct 18 '05
BOARDEmail Vote / Unlisted MeetingBOARDRemanded Remanded → TAC“On 10/18/05, the Board unanimously voted to remand SCR745 to TAC.”
-
Nov 3 '05
TACEmail Vote / Unlisted MeetingTACRecommended for Approval Remanded → RMS“On 11/03/05, TAC unanimously voted to remand SCR745 to RMS. All market segments were present.”
-
Nov 9 '05
RMS RMS MeetingRMSRecommended for Approval Recommended for approval priority 1 · rank 8 priority 1“On 11/09/05, RMS voted to recommend the approval of two subprojects and a priority of 1.1 and rank of 8 for Subproject One, priority of 1.2 and rank of 58.5 for Subproject Two. The motion passed unanimously. All Market segments were present.” — Passed
- Nov 17 '05
-
Dec 1 '05
TAC TAC MeetingTACRecommended for Approval Recommended for approval priority 1 · rank 8 priority 1 · rank 58“On 12/01/05, TAC unanimously voted to recommended approval of two subprojects and a priority of 1.1 and rank of 8 for Subproject One, priority of 1.2 and rank of 58.5 for Subproject Two. All market segments were present.” — Passed→ 12/13/05 BOD
-
Dec 13 '05
BOARD Board of Directors MeetingBOARD Approved Tabled“On 12/13/05, the Board unanimously voted to approve Phases I and II and tabled Phase III.” — Passed→ Board unanimously voted to approve Phases I and II and tabled Phase III.
- Aug 9 '06
-
Sep 13 '06
Listed without action at 9 meetings (Sep 13 '06 – Sep 26 '07)
- Dec 10 '08
- Dec 18 '08
-
Jan 8 '09
Listed without action at 1 meeting
-
Feb 17 '09
BOARDEmail Vote / Unlisted MeetingBOARDApproved Rejected“To approve closing SCR745 without proceeding with Phase III.” — Passed
-
—
Posted since the last meeting