RMGRR #115 · Revision Request
RMGRR115 Manual Work-Around Processes to be Utilized During Extended Retail Outages
ReasonThis RMGRR addresses issues associated with the 12/3/13 ERCOT outage as identified by the Retail Lessons Learned Task Force.
Created2013-03-20
Sections Affected
7.4.17.4.1.17.4.1.37.4.1.47.16.4.3.47.17.3.3.4
Summary
This Retail Market Guide Revision Request (RMGRR) provides guidelines for the use of manual workarounds during an extended outage that affects retail market processing of Customer move ins, move outs and switch hold removals.
Timeline
-
Feb 28 '13
RMSFiled by Kyle Patrick on behalf of the Retail Lessons Learned Task Force
-
Mar 20 '13
RMS Retail Market Subcommittee (RMS) MeetingRMSReferred Referred → RLLTF“To refer RMGRR115 to the Retail Lessons Learned Task Force.” — Passed→ Retail Lessons Learned Task Force for language consideration.
- May 15 '13
-
Jun 3 '13
Listed without action at 2 meetings (Jun 3 '13 – Jun 19 '13)
-
Jul 17 '13
RMS Retail Market Subcommittee (RMS) MeetingRMSRecommended for Approval Recommended for approval Amended by the Jul 16 '13 Oncor comments“To recommend approval of RMGRR115 as amended by the7/16/13 Oncor comments and as revised by RMS.” — Passed→ RMS for Impact Analysis for review.
-
Jul 23 '13
Listed without action at 1 meeting
-
Aug 21 '13
RMS Retail Market Subcommittee (RMS) MeetingRMSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward the 7/17/13 RMS Report and Impact Analysis for RMGRR115 to TAC.” — Passed→ TAC for consideration.
-
Sep 5 '13
TAC Technical Advisory Committee (TAC) MeetingTACApproved Recommended for approval“To approve RMGRR115 as recommended by RMS in the 8/21/13 RMS Report” — Passed
-
—
Posted since the last meeting