RMGRR105  Change to the IDR Meter Requirement Report Due to Inclusion of AMS Meters

Approved sponsor ERCOT posted 2011-10-27 ercot.com
ReasonAlignment with the Protocols to reflect the changes associated with implementation of Nodal Protocol Revision Request (NPRR) 251, Synchronization of PRR845, Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned.
Created2011-11-16
Sections Affected
7.13.2.1
Summary
This Retail Market Guide Revision Request (RMGRR) aligns the Interval Data Recorder (IDR) reporting requirements in the RMG with the Protocols due to the inclusion of Advanced Metering Systems (AMS) meters.