RMGRR #100 · Revision Request
RMGRR100 Texas SET 4.0 including: Acquisition and Transfer of Customers from one REP to Another; Meter Tampering Transactional Solution
ReasonThis RMGRR provides the process for the large transition of ESI IDs as a result of an acquisition pursuant to P.U.C. Subst. R. 25.493, Acquisition and Transfer of Customers from one Retail Electric Provider to Another.
Created2011-07-20
Sections Affected
2.17.3.2.27.3.2.3.17.3.37.3.57.4.1.17.4.1.27.4.1.37.4.1.47.6.2.17.6.2.27.6.3.47.6.3.57.6.3.67.6.3.97.6.5.87.6.6.27.7.17.117.11.17.11.27.11.2.17.11.2.27.11.37.11.47.11.57.11.5.17.11.5.1.17.11.5.1.37.11.5.1.47.11.5.27.11.5.2.17.11.5.2.27.11.5.2.37.11.5.2.47.11.5.2.57.11.5.37.11.5.3.17.11.5.3.27.11.5.3.37.11.5.3.47.11.2 (new)7.11.2.1 (new)7.11.2.2 (new)7.11.2.3 (new)7.11.2.4 (new)7.11.2.4.1 (new)7.11.2.4.1.1 (new)7.11.2.4.1.2 (new)7.11.2.4.1.3 (new)7.11.2.4.1.4 (new)7.11.2.4.1.5 (new)7.11.2.4.2 (new)7.11.2.4.2.1 (new)7.11.2.4.2.2 (new)7.11.2.4.2.3 (new)7.11.2.4.3 (new)7.11.2.4.3.1 (new)7.11.2.4.3.2 (new)7.11.2.4.3.3 (new)7.11.2.4.3.4 (new)7.11.67.11.6.17.11.6.27.11.6.2.17.11.6.37.11.6.3.17.11.6.3.1.17.11.6.3.1.27.11.6.3.27.11.6.47.11.77.11.87.11.97.11.107.12.17.12.27.12.37.12.47.14.57.16.17.16.1.17.16.37.16.4.17.16.4.27.16.4.3.37.16.4.47.17.1.17.17.1.27.17.27.17.3.17.17.3.27.17.3.3.38.3.2.18.3.2.28.3.2.38.3.2.48.3.3.28.3.3.38.3.3.58.3.3.68.3.3.98.3.5.9.3.6.28.3.2.18.3.2.28.3.2.38.3.2.48.3.3.28.3.3.38.3.3.58.3.3.68.3.3.98.3.5.98.3.6.29Appendix D19Appendix D29Appendix F19Appendix F29Appendix F39Appendix F49Appendix F59Appendix F69Appendix F7
Summary
This Retail Market Guide Revision Request (RMGRR) defines the process for Mass Transition of Electric Service Identifiers (ESI IDs) from one Competitive Retailer (CR) to another CR when transitioning due to an acquisition as introduced with Nodal Protocol Revision Request (NPRR) 294,Texas SET 4.0 Including: Acquisition and Transfer of Customers From One REP to Another; Meter Tampering Transactional Solution.
Timeline
-
Jun 30 '11
RMSFiled by Gene Cervenka on behalf of the Market Coordination Team (MCT)
-
Jul 13 '11
Listed without action at 1 meeting
-
Jul 20 '11
RMS RMS MeetingRMSRecommended for Approval Recommended for approval Amended by the Jul 18 '11 Texas SET Working Group comments“To recommend approval of RMGRR100 as amended by the 7/18/11 Texas SET Working Group comments.” — Passed→ RMS for Impact Analysis review.
-
Aug 17 '11
RMS RMS MeetingRMSRecommended for Approval Recommended for approval Forwarded → TAC Amended by the Aug 3 '11 CenterPoint Energy comments“To voted to endorse and forward the 7/20/11 RMS Report as amended by the 8/3/11 CenterPoint Energy comments and the revised Impact Analysis for RMGRR100 to TAC.” — Passed→ TAC for consideration.
-
Sep 1 '11
TAC TAC MeetingTACApproved Recommended for approval“To approve RMGRR100 as recommended by RMS in the 8/17/11 RMS Report.” — Passed
-
—
Posted since the last meeting