RMGRR #62 · Revision Request
RMGRR062 Advanced Metering Implementation Team Requested Change to Letter of Authorization Response
ReasonRemove requirement to provide TDSP charge information
Created2008-08-13
Sections Affected
Section 7.4.1; 9Appendix B1; Section 9Appendix B2; Section 9Appendix B4
Summary
This Retail Market Guide Revision Request (RMGRR) will update the language in Section 7.4.1, Section 9, Appendix B1 and Section 9, Appendix B2 from summary billing to summary usage data. The column "TDSP Charges" will be removed from Section 9, Appendix B4, spreadsheet used to provide Transmission and/or Distribution Provider (TDSP) response. This RMGRR also updates the Spanish version of Letter of Authorization (LOA) in Section 9, Appendix B2
Timeline
-
Jul 17 '08
RMSFiled by Kyle Miller on behalf of Advanced Metering Implementation Team (AMIT)
-
Aug 13 '08
RMS RMS MeetingRMSReferred Referred → AMIT“To refer RMGRR062 to the Advanced Metering Implementation Team (AMIT)” — Passed→ RMS for language consideration
-
Sep 5 '08
Email Vote / Unlisted MeetingWithdrawn
-
Sep 10 '08
Listed without action at 1 meeting