ERCOT·WATCH Search ercot.com  ⌕
RMGRR #37 · Revision Request

RMGRR037  Submission of Switch Requests during a Mass Transition Event

Approved Urgent sponsor Kathy Scott on behalf of TX SET posted 2006-05-31 ercot.com
ReasonTo support the changes submitted in PRR670, First Available Switch Date (FASD) for Switch Requests where Customer no notification is required based upon the event and PUCT Rules, the current Retail Market Guide (RMG) Section 7.11, Mass Customer Transition Process would also require changes to bring both documents in line preventing any discrepancies or issues.
Created2006-06-14
Sections Affected
7.11.5.2.2 Scenario Two: A Date Certain Transition (Off-Cycle) With Either Full or Partial Cooperation from the Losing Competitive Retailer 7.11.7 Competitive Retailer Transition Assumptions
Summary
This PRR introduces revisions to Section 7.11, Mass Customer Transition Process. Several sections were updated, modified and some areas language was deleted where needed in the Retail Market Guide (RMG) to reflect current Market processes and procedures during a mass transition event.
Timeline