PGRR128 Regional Planning Group Discussion of Grid Enhancing Technologies
ReasonStrategic Plan Objective 1
Created2025-07-10
Sections Affected
3.1.1.23.1.2.1and 3.1.10 (new)
Summary
This Planning Guide Revision Request (PGRR) suggests ERCOT should host an annual forum to discuss advanced transmission technologies, commonly referred to as grid enhancing technologies (“GETs”) and high performance conductors (“HPCs”).
Timeline
- Jun 12 '25
-
Jul 10 '25
ROS ROS Meeting - Webex OnlyROSDeferred/Tabled Tabled Referred → PLWG“to table PGRR128 and refer the issue to the Planning Working Group (PLWG)” — Passed→ Language Consideration
- Aug 7 '25
- Sep 11 '25
- Oct 2 '25
- Nov 6 '25
-
Dec 4 '25
Listed without action at 1 meeting
- Jan 8 '26
-
Feb 5 '26
Listed without action at 2 meetings (Feb 5 '26 – Mar 5 '26)
- Apr 2 '26
-
May 7 '26
Listed without action at 1 meeting
-
Jun 4 '26
ROS ROS MeetingROSRecommended for Approval Recommended for approval Amended by the May 12 '26 PLWG comments“to recommend approval of PGRR128 as amended by the 5/12/26 PLWG comments” — Passed→ Impact Analysis
-
Jul 9 '26
ROS ROS Meeting - Webex OnlyROSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 6/4/26 ROS Report and 6/30/26 Impact Analysis for PGRR128” — Passed→ Revision Request Consideration