PGRR #124 · Revision Request

PGRR124  ESR Maintenance Exception to Modifications

Pending sponsor Tesla posted 2025-02-07 sits at ROS next action Language Consideration then to TAC ercot.com
ReasonGeneral system and/or process improvement(s)
Created2025-03-06
Sections Affected
5.2.1.1 (new)
Summary
This Planning Guide Revision Request (PGRR) adds an exemption to the Generator Interconnection or Modification (GIM) process for Energy Storage Resources (ESR)s adding rather than replacing equipment while maintaining the facility’s High Sustained Limit (HSL).
Timeline