PGRR120  SSO Risk Reduction for Generator Interconnection

Approved sponsor ERCOT posted 2024-10-14 ercot.com
ReasonStrategic Plan Objective 1
Created2024-11-07
Approved2025-11-06
Sections Affected
5.2.10 (new) and 5.3.1
Summary
This Planning Guide Revision Request (PGRR) prevents generators from interconnecting to the ERCOT Transmission Grid if the generator would be radial to a series capacitor under N-1 conditions.
Timeline