PGRR #115 · Revision Request
PGRR115 Related to NPRR1234, Interconnection Requirements for Large Loads and Modeling Standards for Loads 25 MW or Greater
ReasonStrategic Plan Objective 1
Created2024-07-11
Approved2025-05-15
Sections Affected
2.14.1.1.14.1.1.25.2.10 (new)5.3.56.6 (new)6.6.1 (new)6.6.2 (new)6.6.3 (new)6.109 (new)9.1 (new)9.2 (new)9.2.1 (new)9.2.2 (new)9.2.3 (new)9.2.4 (new)9.2.5 (new)9.3 (new)9.3.1 (new)9.3.2 (new)9.3.3 (new)9.3.4 (new)9.3.4.1 (new)9.3.4.2 (new)9.3.4.3 (new)9.4 (new)9.5 (new)9.5.1 (new)9.5.2 (new)and 9.6 (new)
Summary
This Planning Guide Revision Request (PGRR) creates a new process for studying the reliability impacts of all Large Loads (as defined in the accompanying NPRR1234) seeking to interconnect to the ERCOT System. As with the Full Interconnection Study (FIS) required for proposed Generation Resources, this PGRR requires a Large Load Interconnection Study (LLIS) for each new Large Load meeting applicability requirements that is proposed to interconnect to the ERCOT System. Like the FIS, the LLIS will consist of a similar suite of studies conducted by one or more affected Transmission Service Providers (TSPs). This PGRR describes these studies in detail and establishes timelines for the review of these studies and the completion of other steps in the interconnection process. This PGRR also: requires all Large Loads evaluated via the LLIS to be included in the existing quarterly stability assessment prior to Initial Energization; adds additional reliability performance criteria for the inclusion and evaluation of Large Loads in planning studies; adds requirements that must be met prior to including a Large Load in the ERCOT Network Operations Model; and establishes required interconnection equipment for both Generation Resources and Large Loads.
Timeline
- May 28 '24
-
Jun 3 '24
Listed without action at 3 meetings (Jun 3 '24 – Jun 12 '24)
-
Jul 11 '24
ROS ROS Meeting - Webex OnlyROSDeferred/Tabled Tabled Referred → PLWG“To table PGRR115 and refer the issue to the Planning Working Group (PLWG)” — Passed→ ROS for consideration
- Jul 16 '24
-
Aug 1 '24
Listed without action at 1 meeting
- Aug 13 '24
- Sep 9 '24
- Sep 24 '24
- Oct 3 '24
- Oct 16 '24
-
Nov 7 '24
Listed without action at 1 meeting
- Nov 12 '24
-
Dec 5 '24
Listed without action at 1 meeting
- Dec 18 '24
- Jan 9 '25
- Jan 29 '25
-
Feb 6 '25
ROS ROS Meeting - Webex OnlyROSRecommended for Approval Recommended for approval Amended by the Feb 5 '25 CenterPoint comments“To recommend approval of PGRR115 as amended by the 2/5/25 CenterPoint comments” — Passed→ ROS for Impact Analysis consideration
-
Mar 6 '25
ROS ROS MeetingROSRecommended for Approval Recommended for approval Forwarded → TAC Amended by the Feb 14 '25 ERCOT Steel Mills comments“To endorse and forward to TAC the 2/6/25 ROS Report as amended by the 2/14/25 ERCOT Steel Mills comments and the 5/28/24 Impact Analysis for PGRR115” — Passed→ TAC for consideration
-
Mar 26 '25
TAC TAC MeetingTACRecommended for Approval Recommended for approval Amended by the Mar 6 '25 ROS comments“To recommend approval of PGRR115 as recommended by ROS in the 3/6/25 ROS Report as revised by TAC” — Passed→ Board for consideration
- Apr 7 '25
-
Apr 8 '25
BOARDEmail Vote / Unlisted MeetingBOARDRecommended for Approval Recommended for approval“To recommend approval of PGRR115 as recommended by TAC in the 3/26/25 TAC Report” — Passed→ PUCT for consideration
-
May 15 '25
PUCTPUCTApproved Approved“To approve PGRR115 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
Jul 15 '25
Listed without action at 10 meetings (Jul 15 '25 – Jun 1 '26)