PGRR #103 · Revision Request

PGRR103  Establish Time Limit for Generator Commissioning Following Approval to Synchronize

Approved sponsor ERCOT posted 2022-12-21 ercot.com
ReasonAddresses current operational issues
Created2023-01-05
Approved2023-10-12
Sections Affected
5.5
Summary
This Planning Guide Revision Request (PGRR) requires an Interconnecting Entity to complete all conditions for commercial operation of a Generation Resource or Energy Storage Resource (ESR) within 180 days of receiving approval for Initial Synchronization from ERCOT.