PGRR #98 · Revision Request
PGRR098 Consideration of Load Shed in Transmission Planning Criteria
ReasonAddresses current operational issues
Created2021-12-02
Approved2022-05-12
Sections Affected
4.1.1.14.1.1.8 (new)
Summary
This Planning Guide Revision Request (PGRR) adds language to the existing reliability performance criteria to allow a corrective action plan to be developed under certain outage scenarios.
Timeline
- Nov 8 '21
-
Dec 2 '21
ROS ROS Meeting by Webex OnlyROSDeferred/Tabled Tabled Referred → PLWG“To table PGRR98 and refer the issue to PLWG” — Passed→ ROS for Consideration
- Jan 6 '22
-
Feb 7 '22
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Amended by the Feb 1 '22 ERCOT comments“to recommend approval of PGRR098 as amended by the 2/1/22 ERCOT comments” — Passed→ Impact Analysis Consideration
-
Mar 3 '22
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 2/7/22 ROS Report and Impact Analysis for PGRR098” — Passed→ Revision Request Consideration
- Mar 30 '22
-
Apr 13 '22
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of PGRR098 as recommended by ROS in the 3/3/22 ROS Report; with a recommended effective date of January 1, 2024 for Section 4.1.1.8 and upon system implementation for the remainder of PGRR098” — Passed→ Revision Request Consideration
-
Apr 28 '22
BOARD Board of Directors MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of PGRR098 as recommended by TAC in the 4/13/22 TAC Report” — Passed→ Revision Request Consideration
-
May 12 '22
PUCTPUCTApproved Approved“to approve PGRR098 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization” — Passed
- Jun 11 '24