PGRR #94 · Revision Request
PGRR094 Clarify Notification Requirement for Generator Construction Commencement or Completion
ReasonAddresses current operational issues; Administrative
Created2021-08-05
Approved2021-10-28
Sections Affected
5.3.2
Summary
This Planning Guide Revision Request (PGRR) aligns Section 5.3.2 with current practices by greyboxing item (7)(c), which requires submission of project construction start and completion dates, until system implementation in the Resource Integration and Ongoing Operations (RIOO) – Integration Services system.
Timeline
- Jul 21 '21
-
Aug 5 '21
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval“to recommend approval of PGRR094 as submitted” — Passed→ Impact Analysis Consideration
- Aug 17 '21
-
Sep 2 '21
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Forwarded → TAC priority 2022 · rank 3540“to endorse and forward to TAC the 8/5/21 ROS Report and the Revised Impact Analysis for PGRR094 with a recommended priority of 2022 and rank of 3540” — Passed→ Revision Request Consideration
-
Sep 16 '21
PRS PRS Meeting by Webex Only“To endorse the ROS recommended priority of 2022 and rank of 3540 for PGRR094”
-
Sep 29 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of PGRR094 as recommended by ROS in the 9/2/21 ROS Report; and the Revised Impact Analysis” — Passed→ Revision Request Consideration
-
Oct 22 '21
BOARD Board of Directors Special MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of PGRR094 as recommended by TAC in the 9/29/21 TAC Report” — Passed→ Revision Request Consideration
-
Oct 28 '21
PUCTPUCTApproved Approved“To approve PGRR094 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021” — Passed
- Oct 24 '24
-
Dec 19 '24
Listed without action at 1 meeting