PGRR #93 · Revision Request
PGRR093 Replace Inadvertent Deletions in Section 5
ReasonAdministrative
Created2021-07-08
Approved2021-10-28
Sections Affected
5.2.5 and 5.2.9.1
Summary
This Planning Guide Revision Request (PGRR) reinserts three requirements into the Board-approved graybox language for PGRR082, Revise Section 5 and Establish Small Generation Interconnection Process, that were inadvertently removed in the revisions made by PGRR082. These three requirements are necessary to facilitate ERCOT transmission planning and resource adequacy studies.
Timeline
- Jun 23 '21
-
Jul 8 '21
ROS ROS Meeting by Webex OnlyROSDeferred/Tabled Tabled Referred → PLWG“to table PGRR093 and refer the issue to the Planning Working Group (PLWG)” — Passed→ Language Consideration
- Jul 20 '21
-
Aug 5 '21
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Amended by the Jul 30 '21 ERCOT comments“to recommend approval of PGRR093 as amended by the 7/30/21 ERCOT comments” — Passed→ Impact Analysis Consideration
- Aug 17 '21
-
Sep 2 '21
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 8/5/21 ROS Report and Impact Analysis for PGRR093” — Passed→ Revision Request Consideration
-
Sep 29 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of PGRR093 as recommended by ROS in the 9/2/21 ROS Report” — Passed→ Revision Request Consideration
-
Oct 22 '21
BOARD Board of Directors Special MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of PGRR093 as recommended by TAC in the 9/29/21 TAC Report” — Passed→ Revision Request Consideration
-
Oct 28 '21
PUCTPUCTApproved Approved“to approve PGRR093 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021” — Passed
-
—
Posted since the last meeting