PGRR #92 · Revision Request
PGRR092 Related to NPRR1077, Extension of Self-Limiting Facility Concept to Settlement Only Generators (SOGs) and Telemetry Requirements for SOGs
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2021-06-03
Approved2021-12-16
Sections Affected
5.2.3
Summary
This Planning Guide Revision Request (PGRR) allows an Interconnecting Entity (IE) proposing a Settlement Only Generator (SOG) to designate that SOG as part of a Self-Limiting Facility for the purposes of the Generator Interconnection or Modification (GIM) process. The PGRR is consistent with NPRR1077, which broadens the Self-Limiting Facility concept in the Protocols to allow SOGs to be designated as part of a Self-Limiting Facility.
Timeline
- May 19 '21
-
Jun 3 '21
ROS ROS Meeting by Webex OnlyROSDeferred/Tabled Tabled Referred → OWG Referred → PLWG“to table PGRR092 and refer the issue to the Operations Working Group (OWG) and Planning Working Group (PLWG)” — Passed→ Language Consideration
- Jul 8 '21
-
Jul 13 '21
Listed without action at 3 meetings (Jul 13 '21 – Aug 19 '21)
-
Sep 2 '21
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval“to recommend approval of PGRR092 as submitted” — Passed→ Impact Analysis Consideration
-
Oct 7 '21
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 9/2/21 ROS Report and the Impact Analysis for PGRR092” — Passed→ Revision Request Consideration
-
Nov 29 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of PGRR092 as recommended by ROS in the 11/17/21 ROS Report” — Passed→ Revision Request Consideration
-
Dec 10 '21
BOARDEmail Vote / Unlisted MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of PGRR092 as recommended by TAC in the 11/29/21 TAC Report” — Passed→ Revision Request Consideration
-
Dec 16 '21
PUCTPUCTApproved Recommended for approval“to approve PGRR092 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021.Result: Passed” — Passed