PGRR #91 · Revision Request
PGRR091 FIS Application Completion 60-Day Limit
ReasonAddresses current operational issues
Created2021-06-03
Approved2021-08-19
Sections Affected
5.35.4.2
Summary
This Planning Guide Revision Request (PGRR) establishes a limit for Interconnecting Entities (IEs) to complete an application to request a Full Interconnection Study (FIS) within 60 days of submittal. An FIS will be considered not to have been requested if the application is not completed within 60 days.
Timeline
- May 18 '21
-
Jun 3 '21
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Amended by the ROS comments“to recommend approval of PGRR091 as revised by ROS” — Passed→ Impact Analysis Consideration
-
Jul 8 '21
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Forwarded → TAC priority 2022 · rank 3530“to endorse and forward to TAC the 6/3/21 ROS Report and the Impact Analysis for PGRR091 with a recommended priority of 2022 and rank of 3530” — Passed→ Revision Request Consideration
-
Jul 28 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of PGRR091 as recommended by ROS in the 7/8/21 ROS Report; and the Revised Impact Analysis” — Passed→ Revision Request Consideration
-
Aug 10 '21
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDRecommended for Approval Recommended for approval“To recommend approval of PGRR091 as recommended by TAC in the 7/28/21 TAC Report” — Passed→ PUCT for consideration
-
Aug 19 '21
PUCTPUCTApproved Approved“to approve PGRR091 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307” — Passed
-
—
Posted since the last meeting