PGRR088  Include Financial Security Amount in the Monthly Generator Interconnection Status Report

Approved sponsor Reliant posted 2020-09-28 ercot.com
ReasonMarket efficiencies or enhancements
Created2020-11-05
Approved2021-06-08
Sections Affected
5.5.4
Summary
This Planning Guide Revision Request (PGRR) increases the transparency of generation interconnection facility costs by including the financial security amount sufficient to fund the interconnection facilities in the ERCOT monthly Generator Interconnection Status report.