PGRR #86 · Revision Request
PGRR086 Related to RRGRR027, Clarify Models Required to Proceed with an FIS
ReasonOther: Improve ability for REs and IEs to complete an FIS application based on the models required to facilitate scoping meetings, enter an FIS agreement, and start most studies
Created2020-10-08
Approved2021-02-09
Sections Affected
5.3 and 5.7.1
Summary
This Planning Guide Revision Request (PGRR) clarifies the models Resource Entities (REs) and Interconnecting Entities (IEs) are required to provide to complete a Full Interconnection Study (FIS) application. Dynamic model data and model quality tests should be provided prior to the start of a stability study.
Timeline
-
Sep 18 '20
ROSFiled by Enel Green Power North America
-
Oct 8 '20
ROS ROS Meeting by Webex OnlyROSDeferred/Tabled Tabled Referred → PLWG“to table PGRR086 and refer the issue to the Planning Working Group (PLWG)” — Passed→ Language Consideration
- Oct 19 '20
-
Nov 5 '20
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval“to recommend approval of PGRR086 as submitted” — Passed→ Impact Analysis Consideration
-
Dec 3 '20
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 11/5/20 ROS Report and Impact Analysis for PGRR086” — Passed→ Revision Request Consideration
-
Jan 27 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“to recommend approval of PGRR086 as recommended by ROS in the 12/3/20 ROS Report” — Passed→ Revision Request Consideration
-
Feb 9 '21
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved Recommended for approval“to approve PGRR086 as recommended by TAC in the 1/27/21 TAC Report” — Passed
-
—
Posted since the last meeting