PGRR #83 · Revision Request
PGRR083 Add RPG Project Number and TPIT Revisions
ReasonOther: Allows for better tracking of RPG projects over time
Created2020-08-06
Approved2020-12-08
Sections Affected
3.1.4.23.1.56.4.3
Summary
This Planning Guide Revision Request (PGRR) adds a requirement for ERCOT to assign a Regional Planning Group (RPG) project number for projects submitted for RPG review. It also removes the specification of some Transmission Service Provider (TSP) provided Transmission Project Information Tracking (TPIT) information from the Planning Guide. The ROS-approved SSWG Procedure Manual will be updated to contain the complete specification for TSP-provided TPIT information. This PGRR also addresses a discrepancy related to the RPG comment period in paragraph (1) of Section 3.1.4.2.
Timeline
- Jul 1 '20
-
Jul 20 '20
Listed without action at 1 meeting
-
Aug 6 '20
ROS ROS MeetingROSDeferred/Tabled Tabled Referred → PLWG“to table PGRR083 and refer the issue to the Planning Work Group (PLWG)” — Passed→ Language Consideration
- Aug 19 '20
-
Sep 3 '20
ROS ROS MeetingROSRecommended for Approval Recommended for approval“to recommend approval of PGRR083 as submitted” — Passed→ Impact Analysis Consideration
-
Oct 8 '20
ROS ROS Meeting by Webex OnlyROSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 9/3/20 ROS Report and the Impact Analysis for PGRR083” — Passed→ Revision Request Consideration
-
Oct 28 '20
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval Amended by the Oct 20 '20 ERCOT comments“to recommend approval of PGRR083 as recommended by ROS in the 10/8/20 ROS Report as amended by the 10/20/20 ERCOT comments” — Passed→ Revision Request Consideration
-
Dec 8 '20
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved Recommended for approval“to approve PGRR083 as recommended by TAC in the 10/28/20 TAC Report” — Passed
-
—
Posted since the last meeting