ERCOT·WATCH Search ercot.com  ⌕
PGRR #76 · Revision Request

PGRR076  Improvements to Generation Resource Interconnection or Change Request (GINR) Process

Approved sponsor ERCOT posted 2019-10-23 ercot.com
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2019-11-07
Approved2020-08-11
Sections Affected
5.1.15.2.15.4.15.4.2.15.4.45.4.55.4.85.7.1and 5.9
Summary
This Planning Guide Revision Request (PGRR) proposes a number of small changes to the Generation Resource Interconnection or Change Request (GINR) process as discussed at various Resource Integration Workshops. The changes include the value that must be increased to meet paragraph (1)(b)(i) of Section 5.1.1; specifying that the proposed Commercial Operations Date entered in the initial GINR application must be 15 months or greater than the date of the application; redefinition of the Security Screening Study output; creation of separate reports for the Full Interconnection Study (FIS); reactive study coordination; and clarification when the dynamic data model should be submitted to meet the quarterly stability assessment prerequisite deadlines.
Timeline