PGRR #72 · Revision Request

PGRR072  Treatment of Generation Resource Retirement and Mothball in Regional Transmission Plan and Geomagnetic Disturbance Vulnerability Assessment

Approved sponsor ERCOT posted 2019-06-26 ercot.com
ReasonMarket efficiencies or enhancements
Created2019-07-11
Approved2019-10-08
Sections Affected
3.1.4.1.13.1.86.11
Summary
This Planning Guide Revision Request (PGRR) allows ERCOT, in collaboration with stakeholders, to set a Generation Resource to out of service in Regional Transmission Plan and Geomagnetic Disturbance (GMD) Vulnerability Assessment base cases prior to receiving a Notification of Suspension of Operations (NSO), provided the Resource Entity notifies ERCOT of its intent to retire/mothball the Generation Resource and/or makes a public statement of its intent to retire/mothball the Generation Resource.