PGRR #71 · Revision Request
PGRR071 Update Interconnection Process Timetables to Align with NPRR926
ReasonAdministrative
Created2019-07-11
Approved2019-12-10
Sections Affected
5.7.5
Summary
This Planning Guide Revision Request (PGRR) updates information in Section 5.7.5 to align with Nodal Protocol Revision Request (NPRR) 926, Removal of 90-Day Period Between SSR Study Approval and Synchronization, which was approved by the ERCOT Board on June 11, 2019.
Timeline
- Jun 19 '19
-
Jul 11 '19
ROS ROS MeetingROSDeferred/Tabled Tabled Referred → PLWG“to table PGRR071 and refer the issue to the Planning Working Group (PLWG)” — Passed→ Language Consideration
- Jul 16 '19
-
Aug 8 '19
Listed without action at 3 meetings (Aug 8 '19 – Sep 18 '19)
-
Oct 3 '19
ROS ROS MeetingROSRecommended for Approval Recommended for approval Amended by the ROS comments“to recommend approval of PGRR071 as revised by ROS” — Passed→ Impact Analysis Consideration
-
Nov 7 '19
ROS ROS MeetingROSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 10/3/19 ROS Report and the Impact Analysis for PGRR071” — Passed→ Revision Request Consideration
-
Nov 20 '19
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of PGRR071 as recommended by ROS in the 11/7/19 ROS Report” — Passed→ Revision Request Consideration
-
Dec 10 '19
BOARD Board of Directors MeetingBOARDApproved Approved“to approve PGRR071 as recommended by TAC in the 11/20/19 TAC Report” — Passed
-
—
Posted since the last meeting