PGRR #63 · Revision Request
PGRR063 Transmission Interconnection Study
ReasonRegulatory requirements
Created2018-05-03
Approved2018-10-09
Sections Affected
3.1.9 (new)
Summary
This Planning Guide Revision Request (PGRR) outlines the process to evaluate the reliability impact of any transmission projects 100 kV or above that are expected to be in-service before the completion of the next Regional Transmission Plan and were not included in the current Regional Transmission Plan, a Regional Planning Group (RPG) project submission, or a Generation Interconnection or Change Request (GINR) study. The intent of the added language is to satisfy Requirement R1 of the North America Electric Reliability Corporation (NERC) Reliability Standard FAC-002-2, Facility Interconnection Studies. By definition, these projects would include Tier 4 transmission projects that are connected at or above 100 kV.
Timeline
- Apr 17 '18
-
Apr 25 '18
Listed without action at 1 meeting
-
May 3 '18
ROS ROS MeetingROSDeferred/Tabled Tabled Referred → PLWG“To table PGRR063 and refer the issue to the Planning Working Group (PLWG).” — Passed→ Language Consideration
- May 22 '18
-
May 23 '18
Listed without action at 3 meetings (May 23 '18 – Jun 18 '18)
-
Jul 12 '18
ROS ROS MeetingROSRecommended for Approval Recommended for approval Amended by the ROS comments“To recommend approval of PGRR063 as revised by ROS.” — Passed→ Impact Analysis Consideration
-
Aug 9 '18
ROS ROS MeetingROSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward to TAC the 7/12/18 ROS Report and Impact Analysis for PGRR063.” — Passed→ Revision Request Consideration
-
Sep 26 '18
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of PGRR063 as recommended by ROS in the 8/9/18 ROS Report.” — Passed→ Revision Request Consideration
-
Oct 9 '18
BOARD Board of Directors MeetingBOARDApproved Approved“To approve PGRR063 as recommended by TAC in the 9/26/18 TAC Report.” — Passed