ERCOT·WATCH Search ercot.com  ⌕
PGRR #55 · Revision Request

PGRR055  Planning Guide Revision Request Process

Approved sponsor ERCOT posted 2017-01-10 ercot.com
ReasonMarket efficiencies or enhancements
Created2017-01-25
Approved2017-04-04
Sections Affected
1.2.11.2.31.2.41.2.4.11.2.4.21.2.4.31.2.4.41.2.4.51.2.4.61.2.4.71.2.4.81.2.4.91.2.4.101.2.4.111.2.4.131.2.5and 1.2.6
Summary
This Planning Guide Revision Request (PGRR) refines the process for revising the Planning Guide so that PGRRs are originally considered at the voting Subcommittee level. These process changes were discussed at the 8/25/16 TAC/TAC Subcommittee Structural and Procedural Review, the 9/29/16 TAC meeting, and the 10/10/16 HR & Governance Committee meeting.
Timeline