PGRR #53 · Revision Request
PGRR053 Addition of Proposed Generation Resources to the Planning Models
ReasonAddresses current operations issues; Market efficiencies or enhancements
Created2016-10-19
Approved2017-02-14
Sections Affected
6.9; 8 Attachment B
Summary
This Planning Guide Revision Request (PGRR) modifies the conditions that need to be met prior to including proposed Generation Resources in the planning models. This proposal includes limiting the initial data required for inclusion in the Steady State Working Group (SSWG) base cases to the data provided for the Full Interconnection Studies (FISs). ERCOT’s System Planning Monthly Status Reports consistently indicate a significant amount of proposed Generation Resources meeting all existing inclusion conditions (Standard Generation Interconnection Agreement (SGIA), applicable permits, notice to proceed, and financial security) with the exception of providing sufficient data required as indicated in the Resource Registration Glossary. The exclusion of the proposed Generation Resources from the Planning Models which have met all other inclusion conditions except for providing sufficient Resource Asset Registration Form (RARF) data has created a need to unnecessarily use extraordinary Dispatch conditions in the SSWG base cases. This PGRR will allow SSWG to utilize more representative generation Dispatch scenarios in their base cases.
Timeline
- Sep 29 '16
- Oct 19 '16
-
Nov 16 '16
PLWGEmail Vote / Unlisted MeetingPLWGRecommended for Approval Recommended for approval Amended by the PLWG comments“To recommend approval of PGRR053 as revised by PLWG.” — Passed→ Impact Analysis Consideration
-
Dec 21 '16
PLWG PLWG MeetingPLWGRecommended for Approval Recommended for approval Forwarded → ROS“To endorse and forward to ROS the 11/16/16 PLWG Report and Impact Analysis for PGRR053.” — Passed→ Revision Request Consideration
-
Jan 12 '17
ROS ROS MeetingROSRecommended for Approval Recommended for approval“To recommend approval of PGRR053 as recommended by PLWG in the 12/21/16 PLWG Report.” — Passed→ Revision Request Consideration
- Jan 25 '17
-
Jan 26 '17
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of PGRR053 as recommended by ROS in the 1/12/17 ROS Report and as revised by TAC.” — Passed→ Revision Request Consideration
- Feb 2 '17
-
Feb 14 '17
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“To approve PGRR053 as recommended by TAC in the 1/26/17 TAC Report.” — Passed