PGRR051  Alignment with NPRR792, Changing Special Protection System (SPS) to Remedial Action Scheme (RAS)

Approved sponsor ERCOT posted 2016-07-27 ercot.com
ReasonRegulatory Requirements
Created2016-08-17
Approved2016-12-13
Sections Affected
6.2.36.4.1
Summary
This Planning Guide Revision Request (PGRR) aligns the Planning Guides with North American Electric Reliability Corporation (NERC) Reliability Standard definition for Special Protection System (SPS) and for consistency uses Remedial Action Scheme (RAS) and Automatic Mitigation Plan (AMP) where applicable in place of SPS.
Timeline