PGRR #29 · Revision Request
PGRR029 Deadline for Regional Transmission Plan
ReasonAt its 2/14/13 meeting, ROS directed that the Planning Working Group (PLWG) develop a PGRR that establishes an annual December 31st deadline for the Regional Transmission Plan (Operations and Planning Synchronization Task Force (OPSTF) recommendation 3a).
Created2013-05-22
Approved2013-11-19
Sections Affected
3.1.1.23.1.1.43.1.4
Summary
This Planning Guide Revision Request (PGRR) establishes an annual deadline of December 31st for ERCOT to complete the Regional Transmission Plan. This PGRR also proposes a non-substantive correction in Section 3.1.1.4.
Timeline
- Apr 26 '13
-
May 22 '13
PLWG Planning Working Group (PLWG) MeetingPLWGRecommended for Approval Recommended for approval“Consensus to recommend approval of PGRR029 as submitted”→ PLWG IA Review
-
Jun 26 '13
PLWG Planning Working Group (PLWG) MeetingPLWGRecommended for Approval Recommended for approval Forwarded → ROS“To endorse and forward the 5/22/13 PLWG Report and Impact Analysis for PGRR029 to ROS”→ ROS Consideration
-
Jul 11 '13
ROS Reliability and Operations Subcommittee (ROS) MeetingROSRecommended for Approval Recommended for approval“To recommend approval of PGRR029 as recommended by PLWG in the 6/26/13 PLWG Report” — Passed→ TAC Consideration
-
Sep 5 '13
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval Recommended for approval“To recommend approval of PGRR029 as recommended by ROS in the 7/11/13 ROS Report” — Passed→ ERCOT Board Consideration
-
Nov 19 '13
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“To approve PGRR029 as recommended by TAC in the 9/5/13 TAC Report.” — Passed
-
—