PGRR #28 · Revision Request

PGRR028  Evaluation of Compliance with Reactive Requirements

Withdrawn sponsor ERCOT posted 2013-02-12 ercot.com
ReasonThis PGRR is in response to concerns raised during the October 15, 2012 Photovoltaic and Storage Workshop. This PGRR proposes to clarify how proposed Generation Resources must design its new facilities.
Created2013-02-27
Sections Affected
5.6.1 (new)
Summary
This Planning Guide Revision Request (PGRR) defines ERCOT’s process for evaluation proposed Generation Resources’ ability to provide reactive power. Protocol Section 3.15, Voltage Support, defines reactive capability requirements for Generation Resources. Paragraph (3) of Protocol Section 16.5, Registration of a Resource Entity requires ERCOT to opine upon the capability of the proposed Generation Resource’s ability to meet these requirements.