PGRR #8 · Revision Request

PGRR008  New Planning Guide Section 5 -- Generation Resource Interconnection or Change Request (formerly "New Planning Guide Section 4 -- Generation Resource Interconnection")

Approved sponsor ERCOT posted 2011-04-14 ercot.com
ReasonCertain responsibilities and requirements related to interconnection studies for new Generation Resources are directly related to transmission planning and are appropriate for inclusion in the Planning Guide. The Planning Guide is being developed as requested by the Reliability and Operations Subcommittee (ROS) and the Technical Advisory Committee (TAC).
Created2011-05-26
Approved2012-02-21
Sections Affected
2.12.2Section 5 (new)
Summary
This Planning Guide Revision Request (PGRR) adds new Section 4, Generation Resource Interconnection. The majority of the language contained in this PGRR comes from the existing ERCOT Generation Interconnection or Change Request Procedure.
Timeline