OBDRR013  Change to the Voltage Levels of Generic Transmission Shadow Prices Caps

Approved sponsor ERCOT posted 2019-04-01 ercot.com
Created2019-05-22
Approved2019-06-11
Sections Affected
Methodology for Setting Maximum Shadow Prices for Network and Power Balance Constraints
Summary
This Other Binding Document Revision Request (OBDRR) revises the voltage levels used to define Generic Transmission Shadow Price Caps for N-1 Constraint Violations in Section 3.5, Generic Values for the Transmission Network System-Wide Shadow Price Caps in SCED. The current, single-value categories of 345 kV, 138 kV, and 69 kV are changed to kV ranges to accommodate transmission equipment that would not directly fall into the three existing categories.