NPRR978 Alignment with Amendments to PUCT Substantive Rule 25.505
ReasonRegulatory requirements
Created2019-11-13
Approved2020-02-11
Sections Affected
3.2.33.2.4 (delete)3.2.54.4.114.4.11.116.11.4.1
Summary
This Nodal Protocol Revision Request (NPRR) incorporates a number of revisions to address recent changes made to Public Utility Commission of Texas (PUCT) Substantive Rule 25.505 in PUCT Project No. 48721, Rulemaking Proceeding To Amend 16 TAC 25.505, Relating to Resource Adequacy in the Electric Reliability Council of Texas Power Region and to Repeal 16 TAC 25.508, Relating to the High System-Wide Offer Cap in the Electric Reliability Council of Texas Power Region. Specifically, this NPRR: • Deletes paragraph (1) of Section 3.2.3 which contained general statements about ERCOT’s system adequacy reporting requirements. Similar language was deleted from Substantive Rule 25.505(d). • Deletes paragraph (2) of Section 3.2.3 which required ERCOT to post a Medium-Term System Adequacy Report. The requirement for this report was removed from Substantive Rule 25.505(d). The following components of the existing Medium-Term System Adequacy Report will be retained pursuant to requirements in other Protocol sections: o Ancillary Service Requirement Methodology, which is also required to be posted on the Market Information System (MIS) Public Area pursuant to paragraph (3) of Protocol Section 1.1, Summary of the ERCOT Protocols Document, due to its inclusion on the Other Binding Documents List. o Long-Term Daily Load Forecast, which is also required to be posted on the MIS Secure Area pursuant to paragraph (1)(b) of Section 3.12, Load Forecasting. o Long-Term Weekly Peak Demand Forecast, which is also required to be posted on the MIS Secure Area pursuant to Section 3.2.2, Demand Forecasts. Since the only remaining content in Section 3.2.3 relates to short-term system adequacy reports, this NPRR also proposes to change the title to Section 3.2.3 to “Short-Term System Adequacy Reports.” • Revises paragraphs (3)(a), (b), (c), (g), and (h) of Section 3.2.3, which relates to short-term adequacy reports, to reflect the requirement in amended Substantive Rule 25.505(d) that information concerning Resource availability be aggregated by Load Zone or area. • Deletes paragraphs (3)(e) and (f) of Section 3.2.3, which required that short-term adequacy reports include daily Ancillary Service requirements and transmission constraints that have a high probability of being binding in Security-Constrained Economic Dispatch (SCED) or the Day-Ahead Market (DAM) given the forecasted system conditions for each week including the effects of any transmission or Resource Outages. The requirement to include this information in ERCOT’s short-term adequacy reports was removed from Substantive Rule 25.505(d). • Deletes Section 3.2.4. The requirement for this report was removed from Substantive Rule 25.505 (formerly paragraph (c)). • Changes instances of “48 hours” to “three days” in Section 3.2.5 to align with a similar change made in Substantive Rule 25.505(f). • Changes instances of “annual Resource adequacy cycle” to “year” in Sections 4.4.11 and 4.4.11.1 to align with a similar change made in Substantive Rule 25.505(g). • Revises the formula for Initial Minimum Current Exposure (IMCE) in paragraph (2) of Section 16.11.4.1 to be based on the System-Wide Offer Cap (SWCAP) in effect, rather than the greater of the SWCAP and the Value of Lost Load (VOLL). This change reflects new Substantive Rule 25.505(g)(6)(E), which states that the VOLL will be equal to the value of the SWCAP in effect (i.e., SWCAP and VOLL will not vary from one another).
Timeline
- Oct 29 '19
-
Nov 13 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“to recommend approval of NPRR978 as submitted” — Passed→ Impact Analysis Consideration
-
Dec 12 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2020 · rank 240“to endorse and forward to TAC the 11/13/19 PRS Report and Impact Analysis for NPRR978 with a recommended priority of 2020 and rank of 240” — Passed→ Revision Request Consideration
-
Jan 29 '20
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of NPRR978 as recommended by PRS in the 12/12/19 PRS Report” — Passed→ Revision Request Consideration
-
Feb 11 '20
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“to approve NPRR978 as recommended by TAC in the 1/29/20 TAC Report” — Passed
- Nov 11 '20
-
Dec 10 '20
Listed without action at 3 meetings (Dec 10 '20 – Feb 9 '21)