NPRR #973 · Revision Request
NPRR973 Add Definitions for Generator Step-Up and Main Power Transformer
ReasonAddresses current operational issues
Created2019-10-10
Approved2020-08-11
Sections Affected
2.12.23.10.7.1.4and 3.10.7.2
Summary
This Nodal Protocol Revision Request (NPRR) adds definitions for Generator Step-Up (GSU) and Main Power Transformer (MPT) to the Nodal Protocols and clarifies their uses.
Timeline
- Sep 25 '19
-
Oct 10 '19
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → ROS“to table NPRR973 and refer the issue to ROS” — Passed→ Language Consideration
- Nov 7 '19
- Nov 12 '19
-
Nov 13 '19
Listed without action at 6 meetings (Nov 13 '19 – Jan 9 '20)
-
Jan 16 '20
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Jan 10 '20 ROS comments“to recommend approval of NPRR973 as amended by the 1/10/20 ROS comments” — Passed→ Impact Analysis Consideration
- Feb 6 '20
-
Feb 13 '20
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 1/16/20 PRS Report and Impact Analysis for NPRR973” — Passed→ Revision Request Consideration
-
Jun 24 '20
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of NPRR973 as recommended by PRS in the 2/13/20 PRS Report” — Passed→ Revision Request Consideration
-
Aug 11 '20
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved Approved“to approve NPRR973 as recommended by TAC in the 6/24/20 TAC Report” — Passed
- Oct 15 '20
-
Nov 11 '20
Listed without action at 3 meetings (Nov 11 '20 – Dec 8 '20)