NPRR #965 · Revision Request
NPRR965 GREDP Shutdown Exemption
ReasonAddresses current operational issues; Administrative; Regulatory requirements
Created2019-09-12
Approved2019-12-10
Sections Affected
8.1.1.4.1
Summary
This Nodal Protocol Revision Request (NPRR) excludes from the Generation Resource Energy Deployment Performance (GREDP) calculation the five-minute intervals in which a Quick Start Generation Resource (QSGR) is engaging in the decommitment process under Section 3.8.3.1, Quick Start Generation Resource Decommitment Decision Process, or telemetering SHUTDOWN status.
Timeline
- Aug 5 '19
-
Sep 12 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“to recommend approval of NPRR965 as submitted” — Passed→ Impact Analysis Consideration
-
Oct 10 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2020 · rank 2900“to endorse and forward to TAC the 9/12/19 PRS Report and Impact Analysis for NPRR965 with a recommended priority of 2020 and a rank of 2900” — Passed→ Revision Request Consideration
-
Oct 23 '19
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of NPRR965 as recommended by PRS in the 10/10/19 PRS Report” — Passed→ Revision Request Consideration
-
Dec 10 '19
BOARD Board of Directors MeetingBOARDApproved Approved“to approve NPRR965 as recommended by TAC in the 10/23/19 TAC Report” — Passed
-
—
Posted since the last meeting