NPRR #941 · Revision Request
NPRR941 Create a Lower Rio Grande Valley Hub
ReasonMarket efficiencies or enhancements
Created2019-06-13
Approved2019-12-10
Sections Affected
3.5.2.6 (new)3.5.2.6and 3.5.2.7
Summary
This Nodal Protocol Revision Request (NPRR) creates a trading Hub “Lower Rio Grande Valley 138/345 kV Hub (LRGV 138/345)” in the ERCOT lower Rio Grande Valley. The NPRR also excludes this new Hub from the existing ERCOT-wide Hub average and Bus average calculations in Sections 3.5.2.6 and 3.5.2.7.
Timeline
- May 7 '19
-
Jun 13 '19
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → WMS“To table NRR941 and refer the issue to WMS” — Passed→ PRS for consideration
- Jun 24 '19
-
Jul 10 '19
Listed without action at 2 meetings (Jul 10 '19 – Jul 17 '19)
- Aug 5 '19
- Aug 7 '19
-
Aug 15 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Aug 6 '19 DC Energy comments“To recommend approval of NPRR941 as amended by the 8/6/19 DC Energy comments” — Passed→ PRS for Impact Analysis consideration
-
Sep 12 '19
PRS PRS MeetingPRSDeferred/Tabled Tabled“To table NPRR941 for one month” — Passed→ PRS for consideration
- Oct 10 '19
-
Nov 13 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC Amended by the Oct 28 '19 ERCOT comments priority 2020 · rank 2860“To endorse and forward to TAC the 8/15/19 PRS Report as amended by the 10/28/19 ERCOT comments and the Impact Analysis for NPRR941 with a recommended priority of 2020 and rank of 2860” — Passed→ TAC for consideration
-
Nov 20 '19
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR941 as recommended by PRS in the 11/13/19 PRS Report as revised by TAC, and the Revised Impact Analysis” — Passed→ Board for consideration
-
Dec 10 '19
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR941 as recommended by TAC in the 11/20/19 TAC Report” — Passed
-
—
Posted since the last meeting