NPRR #930 · Revision Request
NPRR930 Process, Pricing, and Cost Recovery for Delayed Resource Outages
ReasonAddresses current operational issues. Meets Strategic goals. Market efficiencies or enhancements.
Created2019-04-11
Approved2019-10-08
Sections Affected
2.12.23.1.4.63.1.6.95.15.5.25.6.5 (new)5.6.5.1 (new)5.6.5.2 (new)5.6.5.3 (new)5.7.25.7.45.86.5.7.36.5.9.3.1.1 (new)and 9.5.6
Summary
This Nodal Protocol Revision Request (NPRR) requires ERCOT to use an Outage Adjustment Evaluation (OAE) process to delay accepted or approved Outages after issuing an Advance Action Notice (AAN) to describe the need and providing time for Qualified Scheduling Entities (QSEs) to adjust their Outage plans. A Resource that receives an Outage Schedule Adjustment (OSA) as a result of an OAE will be made whole to its actual costs incurred due to delaying or canceling and rescheduling the Outage and committing the Resource, as appropriate. In addition, it sets an offer floor for the Resource at $4,500/MWh. Together, these changes will encourage Resources to self-commit to avoid the opportunity cost of offering at a very high price, while making them whole if they do follow ERCOT’s instructions. A QSE with a Resource that is unable to return to service due to reliability reasons may update its Outage to a Forced Outage so that it may continue its Outage plans to support the Resource’s longevity and availability during critical Load periods.
Timeline
-
Mar 28 '19
PRSFiled by Citigroup
-
Apr 11 '19
PRS PRS MeetingPRSDeferred/Tabled Urgent status Tabled“To grant NPRR930 Urgent status; to table NPRR930” — Passed→ PRS for consideration
- Apr 24 '19
-
May 9 '19
PRS PRS MeetingPRSDeferred/Tabled Tabled“To table NPRR930 for one month” — Passed→ PRS for consideration
- May 16 '19
- Jun 13 '19
- Jun 25 '19
- Jul 17 '19
-
Aug 15 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Aug 14 '19 Joint comments Forwarded → TAC“To recommend approval of NPRR930 as amended by the 8/14/19 Joint comments as revised by PRS; and to forward to TAC” — Passed→ TAC for consideration
-
Sep 25 '19
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR930 as recommended by PRS in the 8/15/19 PRS Report with a recommended priority of 2020 and rank of 2890” — Passed→ Board for consideration
-
Oct 8 '19
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“To approve NPRR930 as recommended by TAC in the 9/25/19 TAC Report” — Passed
-
—
Posted since the last meeting