ERCOT·WATCH Search ercot.com  ⌕
NPRR #923 · Revision Request

NPRR923  Revision to Weather Responsiveness Determination Process

Approved sponsor Profiling Working Group (PWG) posted 2019-02-08 ercot.com
ReasonAddresses current operational issues
Created2019-03-14
Approved2019-06-11
Sections Affected
11.4.3.1
Summary
This Nodal Protocol Revision Request (NPRR) updates the weather sensitivity process by allowing Transmission and/or Distribution Service Providers (TDSPs) an additional 30 days to complete investigation and execution of the request to revise the Load Profile for a BUSIDRRQ Electric Service Identifier (ESI ID).
Timeline