NPRR #920 · Revision Request

NPRR920  Change to Ramp Rate Calculation in Resource Limit Calculator

Approved sponsor ERCOT posted 2019-01-25 ercot.com
ReasonAddresses current operational issues
Created2019-02-14
Approved2019-04-09
Sections Affected
6.5.7.2
Summary
This Nodal Protocol Revision Request (NPRR) modifies the Resource ramp rate logic in Section 6.5.7.2, Resource Limit Calculator, to dynamically adjust the amount of ramp rate reserved for Regulation Service in Real-Time based on the percentage of Regulation Service being deployed in the opposite direction in Real-Time.