ERCOT·WATCH Search ercot.com  ⌕
NPRR #913 · Revision Request

NPRR913  Generator Interconnection Neutral Project Classification

Rejected sponsor The WInd Coalition posted 2018-12-07 ercot.com
ReasonMarket efficiencies or enhancements
Created2019-01-17
Rejected2019-04-11
Sections Affected
3.11.4.3
Summary
This Nodal Protocol Revision Request (NPRR) addresses the neutrality of projects required to interconnect generation to the ERCOT Transmission Grid, and projects for the reliable operation of the generation under particular conditions described in North American Electric Reliability Corporation (NERC) Standard TPL-001-4 – Transmission System Planning Performance Requirements.
Timeline