NPRR #910 · Revision Request

NPRR910  Clarify Treatment of RUC Resource that has a Day-Ahead Market Three-Part Supply Award

Approved sponsor ERCOT posted 2018-11-28 ercot.com
ReasonAddresses current operational issues
Created2018-12-13
Approved2019-02-12
Sections Affected
5.5.25.6.2and 6.7.5
Summary
This Nodal Protocol Revision Request (NPRR) codifies eligibility, pricing, and Settlement for a Resource that has been awarded a Three-Part Supply Offer in the Day-Ahead Market (DAM) but decides not to operate the Resource in the Real-Time Market (RTM) and subsequently receives a Reliability Unit Commitment (RUC) instruction to operate that Resource.
Timeline